Le Mans Hospital Center
The client’s objectives and expectations
- Project Management Assistance & future connection to the urban heat network.
- Preliminary study on the contractual mode and opportunity study for MGP (Global Performance Contract).
- Contract renewal P1 P2 P3.
- Technical, legal, and financial support for the connection to the network of the new Public Service Delegation Mans Nord Enr’gie.
Our main missions
- Preliminary study of the existing contract,
- Assessment of the current contract,
- Study of consumption,
- Summary of equipment,
- Preliminary study on the contractual mode and opportunity study for MGP (Global Performance Contract),
- Drafting of the tender documents (DCE) in P1P2P3 for the 20 MW central boiler plant,
- Support during the candidate selection procedure,
- Finalization of the contract,
- Technical, legal, and financial support for the future connection to the network of the new DSP Mans Nord Enr’gie.
Project characteristics:
- Le Mans Hospital Center, part of GHT 72,
- MGP study, including the tertiary decree component,
- HVAC scenario: -26% compared to the baseline, with €40 million in works,
- HVAC + complete building scenario: -41% compared to the baseline, with €60 million in works,
- Operation contract for heat distribution installations and softened water,
- P1P2P3 on 20,000 MWh HHV of gas,
- Duration: 5 years in MCI P1P2P3.
Results obtained
- Future connection to the network of the new DSP Mans Nord Enr’gie,
- 10,000 MW of subscribed capacity,
- 100% local energy,
- 100% renewable energy,
- 0% carbon.
It was a real pleasure to work with an engaged client who collaborated with us to co-create a reliable, precise, and well-thought-out contractual tool to ensure: operational guarantees for the central boiler of a hospital where service continuity is paramount, and a move toward a future MGP market with guaranteed energy savings, within the framework of the tertiary decree, thus contributing to the energy transition. Shared technical and environmental values that allowed us to validate, in a second phase, the future connection of the Le Mans Hospital Center to the network of the new DSP Mans Nord Enr’gie.