Dalkia
The client’s objectives and expectations
Development of a master plan for the energy transition at the Aéroports de Paris platforms of Roissy – Charles de Gaulle, aimed at identifying the main achievable areas for improvement (2025-2030).
Our main missions
- Analysis of current and future energy needs,
Simulation of the integration of multiple pieces of equipment according to different scenarios:
- Scenario 1: ThermoFrigoPump 8 MW (cold and heat production) + existing 3 MW wood boiler condenser + 12 MW biomass boiler plant,
- Scenario 2: 10 MW Geothermal,
- Evaluation of investment and operating costs,
- Study of available subsidies,
- Proposed financing plan,
- Economic and legal structuring of projects.
Project specifications
- ADP (Aéroport De Paris) covers about 10% of its heat needs with renewable energies (biomass boiler plant).
- Assumptions on the evolution of the site’s energy needs (in collaboration with ADP and Dalkia).
- Forecasting changes in CO2 price per ton and gas prices.
Results obtained
- Identification of the main areas for improvement achievable during the 2025-2030 period.
- Simulation of the integration of multiple equipment according to different scenarios.
- Proposal of strategic energy solutions for the energy transition.